144 km of Bengaluru Satellite Town Ring Road to Become Operational by November 2026

Share

By Political Bureau, Bangalore Mail

BANGALORE: In a major push to decongest the tech capital’s choked arterial routes, nearly half of the ambitious 288 km Bengaluru Satellite Town Ring Road (STRR) project is set to be fully operational by November 2026.

Once opened, the 144 km continuous ring corridor will allow heavy vehicles and inter-state traffic to bypass core Bengaluru completely, connecting Dobaspet directly to Hosur via Doddaballapura, Devanahalli, Hoskote, and the Karnataka–Tamil Nadu border.

Key Project Milestones & Progress

 Dobaspet–Hoskote Belt: An 80 km stretch running through Doddaballapura and Devanahalli has already been operational for over two years, serving key industrial and commercial freight zones.

 Karnataka Border Link: Construction on the remaining 21 km greenfield segment stretching up to the Tamil Nadu border is near completion, with final safety, surfacing, and load-testing scheduled ahead of the November 2026 launch.

 Tamil Nadu Section: Across the state line, a 35.76 km greenfield road reaching Belagondapalli is over 91% complete and is targeted for commissioning by September 2026.

 Expressway Integration: Combined with a completed 7 km link connected to the Bengaluru–Chennai Expressway, these sections form the seamless 144 km primary ring route.

Faster Airport Access and Reduced Truck Transit

The newly operational corridor is expected to offer a faster alternative route between Hosur and Kempegowda International Airport (KIA) via a direct interchange with the Bengaluru–Chennai Expressway. Traffic planners estimate this will take thousands of commercial trucks off Outer Ring Road (ORR) and inner city routes, significantly cutting down commute times for local commuters.

Constructed by the National Highways Authority of India (NHAI) across six execution packages at an estimated cost of ₹14,655 crore, the overall STRR network spans 243 km in Karnataka and 45 km in Tamil Nadu.

NHAI officials indicated that remaining site work will focus on deck slab construction, concrete curing, road surfacing, guardrail installations, and load testing over the coming months to guarantee structural safety before opening the corridor to public traffic.

bmadmin

Recent Posts

Basavaraj Horatti Resigns as Karnataka Legislative Council Chairman Under Pressure From Congress

By Political Bureau Bangalore Mail BENGALURU: In a major political development in Karnataka, veteran politician…

2 hours ago

Top Bengaluru 5-Star Hotels Under Scanner: Food Safety Raids Hit The Lalit Ashok, Shangri-La

Byline: Metro Bureau Location: Bengaluru BENGALURU: In a major crackdown on food safety across the…

3 hours ago

Following PM Modi’s Precedent,D K Shivakumar Eyes Defence Land for 3 New Lalbagh-Style Parks in Bengaluru

Byline: By Bangalore Mail Political Bureau Location: Bengaluru Taking a page from Prime Minister Narendra…

3 hours ago

Karnataka SIR 2026: Over 1.11 Crore Voters Flagged for Verification; Names Not Deleted, Clarifies EC

Byline: Political Bureau Publication: Bangalore Mail Dateline: BENGALURU BENGALURU: Over 1.11 crore voters across Karnataka—accounting…

1 day ago

Karnataka Cabinet Expansion Backlash: Congress Triggers Damage Control to Pacify Sulking MLAs

By Political Bureau | Bangalore Mail Published: August 06, 2026 BENGALURU: In the wake of…

1 day ago

Namma Metro Reach 6: BMRCL to Energise Underground Third Rail from August 10; Issues High-Voltage Safety Warning

Byline: Political Bureau | Bangalore Mail Published: August 6, 2026 BENGALURU: In a major milestone…

2 days ago