Namma Metro Reach 6: BMRCL to Energise Underground Third Rail from August 10; Issues High-Voltage Safety Warning

Share

Byline: Political Bureau | Bangalore Mail

Published: August 6, 2026

BENGALURU: In a major milestone towards operationalising the Pink Line, the Bangalore Metro Rail Corporation Limited (BMRCL) has issued a public safety notification announcing that the underground stretch of Reach-6 will be progressively energised starting August 10, 2026.

The electrical testing will activate the high-voltage 33kV traction power cables and the 750V DC third-rail power system along the underground corridor connecting Pottery Town to Nagawara.

Phased Energisation Drive

According to BMRCL officials, the power activation on the Reach-6 underground section will take place in four structured phases:

1. Pottery Town to Tannery Town

2. Tannery Town to Venkateshpura

3. Venkateshpura to Kadugondanahalli

4. Kadugondanahalli to Nagawara

Once charged, the third rail—located along the tracks to supply propulsion power to metro trains—will carry continuous high-voltage direct current (750V DC), alongside 33kV alternating current traction power cables running through the tunnels.

Strict Safety Advisory Issued to Public

Highlighting the grave risks associated with live electrical infrastructure, the BMRCL issued a severe warning to unauthorized personnel, local residents, and trespassers.

“Any direct or indirect contact with the 750V DC third rail or the 33kV traction cables can result in electrocution and prove fatal. The public is strictly cautioned against entering or approaching the underground metro tunnels, tracks, or auxiliary sub-stations without official authorization once the charging process begins on August 10,” the BMRCL stated in its advisory

Paving the Way for Trial Runs

The energisation of power cables and third-rail systems is a mandatory prerequisite for static and dynamic trial runs on underground metro corridors. Following successful charging and safety checks, BMRCL plans to begin track testing and trial train runs on this key stretch of the Pink Line, bringing North Bengaluru closer to high-speed metro connectivity.

bmadmin

Recent Posts

15-Year-Old Bengaluru Student Builds ₹13 Lakh Investment Portfolio; Aims to Empower 1 Million Peers in Financial Literacy

Business Bureau | Bangalore Mail Bengaluru Student Achieves ₹13 Lakh Portfolio Benchmark In a city…

1 day ago

City Lights Review: Atmospheric Realism Met by Formulaic Execution in Duniya Vijay’s Latest Crime Drama

Kushinara M D Entertainment Bureau | Bangalore MailBENGALURU: Director Duniya Vijay’s latest directorial venture, City…

2 days ago

Mysuru Dasara 2026: MLC B.S. Shivanna Urges CM to Let ‘Cleanliness Warrior’ Inaugurate State Festival

Political Bureau | Bangalore Mail September 18, 2026 BENGALURU: Member of the Legislative Council (MLC)…

2 days ago

Karnataka Cabinet Grants Official Language Status to Tulu in Coastal Districts

By Political Bureau | Bangalore Mail BANGALORE — In a landmark decision fulfilling a decades-long…

2 days ago

Political Lore: When Dr. Rajkumar’s Dadasaheb Phalke Award Spanned Two Prime Ministers

By Kushinara M D, Entertainment Bureau, Bangalore Mail In the political chronicle of 1996, a…

2 days ago

Anant Nag Conferred Dadasaheb Phalke Award 2024: PM Modi Praises Legendary Kannada Actor⁠

By Entertainment Bureau | Bangalore Mail Published: September 16, 2026 Bengaluru: In a moment of…

5 days ago